Sg. Langat 2

REHABILITATION WORKS AT LANGAT 2 WATER TREATMENT PLANT PROJECT (PHASE 1) PACKAGE 2A

Client: Salcon MMCB AZRB JV Sdn. Bhd.
Products used: Non-woven geotextile of sand container system, Non-woven geotextile, Erosion control mat
Year: 2016

Package 2A of the Langat 2 Water Treatment Plant today received strong interest from companies despite issues raised by the Selangor state government on the Project. The 24-package Langat 2 Water Supply Project is part of the Pahang-Selangor Raw Water Transfer Scheme implemented by the Energy, Green Technology and Water Ministry. The raw water will be transferred to Langat 2 from Sungai Semantan in Pahang through a transfer tunnel where the water will be treated and distributed to the Klang Valley.  The proposed for rehabilitation works to the existing slope of Sg. Langat is approximately 1060m total for both side of the river. Hence, Huls Engineering Sdn Bhd is to supply and install geosynthetic materials for the rehabilitation works at Sg. Langat.